| City Gas in Blue Moon Alley | Widening Songtan Station Road | Sinjang Brick Sidewalks | Sinjang Underground Wiring | |
Blue Moon Alley Gas Line Installation |
||||
|---|---|---|---|---|
| On Jan 23, the installation team showed up at 11:20am without warning to install the two gas boilers (2nd and 3rd floors) for our place. It was a cold, very windy day. By 4:30pm they had finished and departed. In a few hours, the snow started and we got our first significant snowfall of the season. Here are the final photos of Blue Moon Alley. |
![]() 1/24/09 - main road snow removal was done by traffic only |
![]() 1/24/09 - merchants were out early to clear storefront snow |
![]() 1/24/09 - after snow removal, blanket shop opened on time |
|
| In the previous installment, I said they were returning on Dec 23. The temperature that day was -9°c, so they postponed the work. The day after Christmas was warmer — -8°c — so they showed up and started the final residence connections. |
![]() 12/26/08 - two excavators, one working each end of the alley |
![]() 12/26/08 - cross-alley trenches cut where needed |
![]() 12/26/08 - this and following show our installation |
|
![]() 12/26/08 - yellow gas pipe connection already done |
![]() 12/26/08 - this device plays some role in sealing connection |
![]() 12/26/08 - here it's connected to both sides of our connector |
![]() 12/26/08 - hole had been drilled for connector pipe |
|
![]() 12/26/08 - connector pipe is prepared for installation |
![]() 12/26/08 - and work continues to prepare other connections |
![]() 12/26/08 - horizontal hole is completed and pipe installed |
![]() 12/26/08 - and connector to main line is installed |
|
![]() 12/26/08 - wires leading from yellow box to seal connection |
![]() 12/26/08 - next segment of connector pipe is installed |
![]() 12/26/08 - and the vertical pipe is then installed |
![]() 12/26/08 - as work continues on cross-alley connection |
|
![]() 12/26/08 - final pipe installation with ground wire to residence |
![]() 12/26/08 - excavations remain open until pressure is applied |
![]() 12/26/08 - a view of the work from far end of alley |
![]() 12/26/08 - worker installing connection to next residence |
|
![]() 12/26/08 - yellow connector pipe at right to install in side alley |
![]() 12/26/08 - work continued into the night, finishing at 10pm |
![]() 12/27/08 - this is what it looked like early the next morning |
![]() 12/27/08 - and this is our completed external connection |
|
![]() 12/19/08 - this is the source of the water leak |
![]() 12/19/08 - a pump is trying to keep up with the flow |
![]() 12/19/08 - eventually the leak is found and repaired |
![]() 12/19/08 - while another excavation starts near MRAO |
|
![]() 12/19/08 - this is to install a new water connection for the hotel |
![]() 12/19/08 - this time it's a success and done pretty quickly |
With the completion of the gas line installation and the repair of multiple water leaks, the final gas installation with connection to residences is scheduled for Tuesday, Dec 23. Will this be the Christmas present Blue Moon Alley residents have awaited since construction began nearly a month ago? | ||
![]() 12/18/08 - MRAO bridge over muddy section of trench |
![]() 12/18/08 - workers arrived to cover trench with asphalt |
![]() 12/18/08 - and the MRAO bridge is no longer needed |
![]() 12/18/08 - another convoy arrives to attack water problem |
|
![]() 12/18/08 - a pump is left near the area of the water leak |
![]() 12/18/08 - and digging in this section has commenced |
|||
![]() 12/17/08 - day has finally arrived for gas line installation |
![]() 12/17/08 - sandpile behind excavator is for fill around pipe |
![]() 12/17/08 - sand ensures fill pressure around pipe is even |
![]() 12/17/08 - and the digging moves along quickly |
|
![]() 12/17/08 - installing gas line is slow and methodical |
![]() 12/17/08 - the stone fill was done after water line installation |
![]() 12/17/08 - there's a lot of work going on at start |
![]() 12/17/08 - yellow pipe is the next gas line segment |
|
![]() 12/17/08 - another pipe segment is brought out |
![]() 12/17/08 - workers prepare ends of segment for connection |
![]() 12/17/08 - that's a ground wire attached along top of the pipe |
![]() 12/17/08 - installed gas pipe is seen at distant end of trench |
|
![]() 12/17/08 - white wire in this and previous picture measure trench |
![]() 12/17/08 - next segment of gas pipe is ready to be installed |
![]() 12/17/08 - even as water accumulates in the trench |
![]() 12/17/08 - despite water, gas line install continues |
|
![]() 12/17/08 - the next segment of the gas pipe is brought out |
![]() 12/17/08 - worker cuts off end to prepare a leakproof connection |
![]() 12/17/08 - another worker helps to stabilize the pipe |
![]() 12/17/08 - Punee supervises workers as they near the MRAO |
|
![]() 12/17/08 - installation of gas line is done as evening arrives |
![]() 12/16/08 - a quiet day in Blue Moon Alley before next round |
|||
![]() 12/15/08 - detritus remaining from our trench |
![]() 12/15/08 - hotel asked to be connected to water line |
![]() 12/15/08 - workers spent half a day looking for connection |
![]() 12/15/08 - but finally gave up when they couldn't find it |
|
![]() 12/14/08 - this is the hole at the far end of the alley |
![]() 12/14/08 - keeping it open for access to gas connection? |
![]() 12/14/08 - some folks have really dirty shoes today |
The photo at the immediate left is the trench right in front of the MRAO. When they finished filling in the trench, the last fill to go into this area was very wet mud. It was the consistency and color of chocolate pudding and it's taking a long time to dry. Photo below shows it right after they finished filling the trench. |
|
| With the completion of the new new water main installation and the connection of all residences, the gas line installation should now proceed. We're told that the gas installation will re-start on Tuesday, Dec 16 |
![]() 12/11/08 - all of the following day was spent on ours |
![]() 12/12/08 - our connection was finished the next morning |
![]() 12/12/08 - the final two connections were done quickly |
|
![]() 12/10/08 - and were back the next morning in the same hole |
![]() 12/10/08 - it was a painful process to watch them |
![]() 12/10/08 - but they finally completed it |
During the entire time that this work has been going on, the distant end of the alley has remained closed as shown in photos in row below. It has been interesting to watch drivers come zipping in from the main road and see how far they go before realizing they can't go through and must back out. | |
![]() 12/9/08 - the crew worked all day on this one connection |
![]() 12/8/08 - a new crew showed up to connect residences |
![]() 12/8/08 - a slow process finding 40-yr-old water connections |
||
![]() 12/6/08 - the next day, crew was back to finish the pipline |
![]() 12/6/08 - and the excavator is shown tamping down the fill |
On Friday, Dec 5, the excavator was picked up and taken to an emergency repair job. We wondered when it might return. |
![]() 12/4/08 - on a rainy Thursday, excavator remained unused |
|
![]() 12/2/08 - the first task was to reopen the trench |
![]() 12/2/08 - considerably more excavation work was done |
![]() 12/2/08 - the excavator moved along reopening the trench |
![]() 12/2/08 - here it's approaching the military retiree office |
|
![]() 12/2/08 - work was slowed by the need to clean out old stuff |
![]() 12/2/08 - and the new water main pipeline followed |
![]() 12/2/08 - one worker works in trench while three supervise |
![]() 12/2/08 - new pipeline is threaded under existing pipes |
|
![]() 12/2/08 - care must also be taken with existing connections |
![]() 12/2/08 - excavator must also break up the asphalt |
![]() 12/2/08 - by evening, excavator was in front of retiree office |
![]() 12/2/08 - and partly open trench restricted office access |
|
| Monday, Dec 1 - Five days after the water main was broken a new crew showed up to repair/replace the water main |
![]() 12/1/08 - the new crew arrived early to start repairs |
![]() 12/1/08 - after one repair was completed, they moved on |
![]() 12/1/08 - the second repair was not easy and kept reopening |
|
![]() 12/1/08 - the crew worked through the day on the water line |
![]() 12/1/08 - attempting to move the digging further along |
![]() 12/1/08 - at the end of a long day, they loaded the machine |
![]() 12/1/08 - and departed without have gained much ground |
|
![]() 11/25/08 - equipment has been unloading since 7am arrival |
![]() 11/25/08 - soil full of trash from previous job dumped here |
![]() 11/25/08 - setting up equipment to start working |
![]() 11/25/08 - one resident failed to move his car before start |
|
![]() 11/25/08 - long yellow pipes are the main gas line |
![]() 11/25/08 - worker removes sign to prepare for installation |
![]() 11/25/08 - worker starts to cut asphalt; sand piled at right |
![]() 11/25/08 - worker cuts pipes for residence installation |
|
![]() 11/25/08 - 'butt crack' is not limited to plumbers |
![]() 11/25/08 - loader clears space for pedestrians to pass |
![]() 11/25/08 - concrete took more effort to break up and clear |
![]() 11/25/08 - truck with tools and parts for residence installers |
|
![]() 11/25/08 - the hard stuff has been broken up for trench dig |
![]() 11/25/08 - big pieces removed, small pieces go by shovel |
![]() 11/25/08 - gas main pipes are being joined before burial |
![]() 11/25/08 - this is the equipment that is used to join the pipes |
|
![]() 11/25/08 - a ground wire is installed the length of the pipe |
![]() 11/25/08 - home delivery sign removed for meter install |
![]() 11/25/08 - workman later glues sign with this final result |
![]() 11/25/08 - the digging has stopped for some reason |
|
![]() 11/25/08 - aha, broken water pipe halts work for 4 hrs |
![]() 11/25/08 - while workers wait for water repairmen to arrive |
![]() 11/25/08 - first repair didn't work, so back to it again |
![]() 11/25/08 - as night fell, they refilled the trench |
|
![]() 11/25/08 - the gas main pipes remained unburied |
![]() 11/25/08 - the sand was then used to fill the partial trench |
![]() 11/25/08 - all that remains is a scar and a mess when it rains |
![]() 11/25/08 - gas main pipes had been moved to side alley |
|
Songtan Station Road Widening |
||||
![]() 11/11/09 - here's an update on the widening of the road to Songtan Station. The construction is proceeding very slowly as a number of homes and business are being dislocated. |
||||
![]() 11/11/09 - with the construction, remaining road is very narrow |
![]() 11/11/09 - parking along narrow road certainly doesn't help |
![]() 11/11/09 - example of novel rewiring solutions seen here |
![]() 11/11/09 - worker down inside part of new drainage system |
|
![]() 11/11/09 - construction stops at overpass going to main gate |
![]() 11/11/09 - looking back from the overpass toward the station |
![]() 11/11/09 - if road widening continues, will this area be next? |
||
![]() 1/02/09 - a wide view from stairway at the Songtan Station |
![]() 1/02/09 - a view of the same area from ground level |
![]() 1/02/09 - this house looks very nice from here |
||
![]() 1/02/09 - but it's gutted and the bulldozer is coming |
![]() 1/02/09 - this house was still occupied last time we looked |
![]() 1/02/09 - but it's definitely empty now |
![]() 1/02/09 - and this house is pretty much gone |
|
![]() 1/02/09 - rubble from the same house is at the right |
![]() 1/02/09 - another nice and relatively new one is gutted |
![]() 1/02/09 - just past that house, overpass ahead |
||
![]() 1/02/09 - another house near overpass is gutted |
![]() 1/02/09 - the area near the overpass looks like it will present quite a challenge for widening |
|||
![]() 11/26/08 - a view from stairway at the Songtan Station |
![]() 11/26/08 - a view of the same area from ground level |
![]() 11/26/08 - some houses only a few feet behind survived |
![]() 11/26/08 - middle house is empty, house to left is occupied |
|
![]() 11/26/08 - this very large house will soon be demolished |
![]() 11/26/08 - looks like demolition started, but still occupied above |
![]() 11/26/08 - removal is not affecting consecutive buildings |
![]() 11/26/08 - empty below, looks like it's occupied above |
|
![]() 11/02/08 - house near rail line is empty, ready to go |
![]() 11/02/08 - houses to make way for road widening |
![]() 11/02/08 - road extends from Songtan Station |
![]() 11/02/08 - indications are it will go through downtown |
|
![]() 11/02/08 - new sign installed along rail line |
![]() 11/02/08 - advises of noise level from nearby airbase |
![]() 11/02/08 - sign also advises of aircraft 'vibration' |
![]() 11/02/08 - info rotates to provide frequents updates |
|
Sinjang Sidewalks |
||||
![]() 6/20/09 - red asphalt re-paving in alley near 7-11 outside gate |
![]() 6/20/09 - repaving continues but stops at OB House entrance |
![]() 6/20/09 - to the right, re-paving stops halfway down hill |
||
![]() 6/20/09 - alley across from Stereo Club is repaved black |
![]() 6/20/09 - this alley repaving also stops short of the alley end |
![]() 6/20/09 - further along, electrical truck unloading cables |
![]() 6/20/09 - wiring in this area does look like it needs some work |
|
![]() 11/09/08 - workers are back to do some sidewalk repairs |
![]() 11/09/08 - part of the curbing and bricks have been removed |
![]() 11/09/08 - bricks on sand base become uneven quickly |
![]() 11/09/08 - if at first you don't succeed, try, try again |
|
![]() 10/15/08 - concrete poles have been removed |
![]() 10/15/08 - and the associated wires also removed |
|||
![]() 8/16/08 - new sidewalk stones are not wearing well |
![]() 8/16/08 - raised section here presents tripping hazard |
![]() 8/16/08 - especially where concrete has broken off |
![]() 8/16/08 - uneven bricks are problem for handicapped |
|
![]() 5/25/08 - custom-cut pieces are now installed |
![]() 5/25/08 - some work still not completed, no rush though |
![]() 5/25/08 - handicap obstacle remains as an obstacle |
![]() 5/25/08 - sidewalk on other side also looking good |
|
![]() 5/25/08 - outlet for underground utilities |
![]() 5/25/08 - going to be hard keeping it clean |
![]() 5/25/08 - bricks cut to fill a narrow gap |
![]() 5/25/08 - then they got tired of cutting and filling |
|
![]() 5/11/08 - sidewalk upgrade outside gate still a hazard |
![]() 5/11/08 - across from the gate, pedestrian "bridges" installed |
![]() 5/11/08 - concrete troughs being installed for drainage |
![]() 5/11/08 - grate then covers the installed trough |
|
![]() 5/11/08 - further down the street, installation continues |
![]() 5/11/08 - transformer box is hazardous to handicapped |
![]() 5/11/08 - temporary end of the current phase of installation |
![]() 5/11/08 - across the street, tripping hazards are prevalent |
|
![]() 5/11/08 - pedestrian footprints are immortalized forever (or so) |
![]() 5/11/08 - crosswalk situation still a hazard for everyone |
![]() 5/11/08 - a small ditch presents a small pedestrian obstacle |
![]() 5/11/08 - a big ditch is an even greater obstacle, even to cars |
|
![]() 5/04/08 - the Songtan-Sinjang sidewalk is being replaced |
![]() 5/04/08 - the weeks-long project leaves dangers afoot |
![]() 5/04/08 - yellow band is aid for handicapped persons |
![]() 5/04/08 - yellow areas also mark pedestrian crossing points |
|
Sinjang Wire Cleanup |
||||
![]() 11/02/08 - looking down from near Capital Hotel towards gate |
![]() 11/02/08 - closer look reveals no wires hanging above street |
![]() 11/02/08 - from Capital Hotel, view in opposite direction |
![]() 11/02/08 - from Osan main gate, looking left |
|
![]() 7/13/08 - electrical work has moved to my neighborhood |
![]() 7/13/08 - pedestrians continue to walk under the work site |
![]() 7/13/08 - wire workers on the ground, wire cutter above |
![]() 7/13/08 - and bucket truck causes some traffic problems. |
|
![]() 7/13/08 - cut wires hang down from this pole |
![]() 7/13/08 - this pole no longer holds electrical wires |
![]() 7/13/08 - transformers hang uselessly from wireless pole |
![]() 7/13/08 - this alley is scheduled for cleanup in Aug or Sep. |
|
![]() 6/08/08 - cleaning up tangle of exposed wiring has begun |
![]() 6/08/08 - the electric wiring is the first to go underground |
![]() 6/08/08 - outside meter makes it easy for the meter reader |
![]() 6/08/08 - neatness counts, but nearby is example of old way. |
|
|
|
||||