| New Challenger Enlisted Club | McPherson Community Center | ||
New Challenger Enlisted Club |
|||
|---|---|---|---|
![]() 04/12/12 - a better night view of the club taken at early dawn with all lights lit.The lights to the left are family housing tower and parking garage, at right is Community Center. For the best view of this image, try the high resolution version (5.8MB). |
|||
![]() 04/04/12 - let the planting begin and it starting to look better and better. The evergreens in this photo took a beating from high winds today. |
|||
![]() 03/30/12 - a night view of the new club with lights installed and working gives you an idea of how the club will appear as you approach it to partake of its offerings |
|||
![]() 03/28/12 - closer and closer to completion as much of work is now outside. The pile of topsoil at the left in the driveway is on a tarp to prevent 'contaminating' driveway work |
|||
![]() 03/28/12 - a view across the front from the right side |
![]() 03/28/12 - looking from sidewalk on Community Center side |
![]() 03/28/12 - bases for the lights to go in around driveway |
![]() 03/28/12 - looking over bases at front entrance |
![]() 03/28/12 - more bases and installed lights |
![]() 03/28/12 - closer look at topsoil pile and workers near bldg |
![]() 03/28/12 - a look the front from the officers club side |
![]() 03/28/12 - and a look at the lights along the right side |
![]() 02/21/12 - the front of the construction site is now clear and all fencing has been removed so here's the first full panoramic view of the front of the club |
|||
![]() 02/16/12 - a new concrete sidewalk curving up to the front entrance has been poured and covered by blue tarp to cure |
|||
![]() 02/10/12 - an updated look at the side of the club with a lot of construction materials around, so there's much yet to be done |
|||
![]() 02/10/12 - the left side of the club looking very much the same as the previous image, but with more 'stuff' in front |
|||
![]() 02/10/12 - the right side of the club, also looking much the same as the previous image |
|||
![]() 02/10/12 - supports over drainage at driveway exit |
![]() 02/10/12 - supports over drainage at driveway entrance |
||
![]() 12/31/11 - an updated view of the back of the club on New Years Eve with more of the final stages of contstruction visible. |
|||
![]() 12/31/11 - an updated view of the back of the club on New Years Eve with more of the final stages of contstruction visible. |
|||
![]() 12/31/11 - the left side of the club where much of the construction equipment is visible and part of the sidewalk in front of streetside parking. |
|||
![]() 12/31/11 - an updated view of the left front of the club and part of the driveway coming from front entrance. |
|||
![]() 12/31/11 - an updated view of the right front of the club and part of the driveway going up to the front entrance. |
|||
![]() 12/31/11 - an updated view of the right side of the club with large glass windows and decorative lights. |
|||
![]() 12/31/11 - a view across the front from the left side |
![]() 12/31/11 - a better view of the driveway leading to front |
![]() 12/31/11 - a better look at the lights at the right side |
![]() 12/31/11 - closeup of the entrance on the right side |
![]() 12/02/11 - an updated view of the back of the new club with more changes evident as the building gets closer and closer to its final image. |
|||
![]() 12/02/11 - this updated side view of the club shows further progress and the removal of the construction fence reveals the new streetside parking area. |
|||
![]() 12/02/11 - a look at the left side front of the club with driveway under construction. |
![]() 12/02/11 - a look at the right side front of the club. |
||
![]() 11/15/11 - here's another view of the front of the new club. The steel fencing has been removed giving me a chance to get this view before the shorter, cloth fencing at left is completed. |
|||
![]() 11/08/11 - some of the fencing was removed from the front of the club construction giving us a pretty good idea of what the front of the club will look like when completed. (Nice double image of front-end loader, too.) |
|||
![]() 10/28/11 - a lot of finishing work has taken place on the back of the new club with more great weather. Construction completion forecast for Mar 2012, interior furnishing and setup estimated complete about Jun 2012. |
|||
![]() 9/20/11 - with the cool, low-humidity early autumn weather, the time is right for an update of the new club construction against a beautiful blue sky with flecks of clouds. |
|||
![]() 9/20/11 - fancy stonework decorating the side |
![]() 9/20/11 - another look at the front of the club from the Community Center side |
||
![]() 8/28/11 - here's a look at the back of the new club to see the progress on construction on one of the rare rain-free days of this summer when the weather was tolerable. |
|||
![]() 8/07/11 - my excuse this time is that it's just been too hot to go out in the midday sun so this time I took the camera with me for an early morning walk. You can see the sunrise behind at right. |
|||
![]() 8/07/11 - an updated view of the side of the club from the Officers Club side |
![]() 8/07/11 - this is a first-time look at the front of the club from the Community Center side |
||
![]() 7/20/11 - it's been awhile since I got the camera out and got an update image for you to view. Busy time what with moving and then monsoon. For the higest resolution image (2.6MB), click here. |
|||
![]() 7/19/11 - ground level view from the Community Center |
![]() 7/19/11 - a view of the entrance to the construction site |
![]() 7/19/11 - here's a view of the side of the club from the hillside in front of the Officers Club |
|
![]() 5/17/11 - two days after taking the below image, here's a side view from in front of the Officer's Club. For the higest resolution image (3.5MB), click here. |
|||
![]() 5/15/11 - here's a full width, full height update view of the new club taken on a beautiful Sunday as roofing was being put on the highest part of the club.The crane moved while I was switching from camera internal to external memory. For a higher resolution image, click here. Disconnects in stitching due to memory changeover are more evident in this image. |
|||
![]() 4/30/11 - here's a full width, full height view of the new club taken on a rainy Saturday when there was no work being done |
|||
![]() 4/05/11 - the remainder of the roof girders have been emplaced |
|||
![]() 3/22/11 - this is the current state of construction of the new club as seen from the Officers Club parking lot |
|||
![]() 3/10/11 - this is a full view combining the upper and lower images seen below. I found a new (to me) program (autostitch) that make panoramic images a breeze. Stitching is seamless. |
|||
![]() 3/10/11 - this is the upper part of the new club in this view from the Personnel building. It has become too high to take the height in one from this location |
|||
![]() 3/10/11 - this is the lower part of the building viewed from the same second floor location. An attempt to create a double high image by 'sewing' the two images together was not successful. |
|||
![]() 12/21/10 - asphalt is piled by the roadway with care |
![]() 12/21/10 - in hope that a pickup soon will be there |
![]() 12/21/10 - moving the asphalt to the work site |
![]() 12/21/10 - asphalt is dumped and back for more |
![]() 12/21/10 - asphalt is piled by the roadway with care |
![]() 12/21/10 - from O'Club, a look at new enlisted club |
![]() 12/21/10 - the construction has closed the side road |
← Across from construction site, a ROKAF-built monument is ready to be dedicated. I'll try to get details in a future 'Feedback from Jack' entry. |
![]() 12/18/10 - asphalt is piled by the roadway with care |
![]() 12/18/10 - in hope that a pickup soon will be there |
![]() 12/18/10 - moving the asphalt to the work site |
![]() 12/18/10 - asphalt is dumped and back for more |
![]() 12/18/10 - and here comes another load to be added |
![]() 12/18/10 - discarded plastic had kept concrete warm |
![]() 12/18/10 - and now the asphalt is being tamped down |
![]() 12/18/10 - work site in front of Community Center |
![]() 12/18/10 - wet concrete of new sidewalk reflects images |
![]() 12/18/10 - heading back to pick up more concrete |
![]() 12/18/10 - worker smoothes the new concrete |
![]() 12/18/10 - across the way, a new monument goes up |
![]() 12/09/10 - snow and cold has slowed construction |
![]() 12/09/10 - light under plastic prevents freezing |
![]() 12/09/10 - the area in front of the library |
![]() 12/09/10 - buried drainpipe partially visible |
![]() 12/02/10 - revised schedule due to reworking project |
![]() 12/02/10 - the same work area, new schedule |
![]() 12/02/10 - removed sections with dirt still on top |
![]() 12/02/10 - sections awaiting re-installation |
![]() 12/02/10 - lowering a section into the trench |
![]() 12/02/10 - looking back at the same work crew |
![]() 12/02/10 - area in front of library has been completed |
![]() 12/02/10 - also complete near shopping mall parking |
![]() 11/23/10 - the roadside closure supporting the new enlisted club is seen here in front of the theater, taken the day after the planned completion date of this project |
|||
![]() 11/23/10 - entrance to shopping mall parking |
![]() 11/23/10 - road between shopping mall and library |
![]() 11/23/10 - exit from libarary parking lot |
![]() 11/23/10 - area in front of Community Center |
![]() 11/23/10 - torn up sidewalk along front of future club |
![]() 11/23/10 - opening in fence where connection will be made |
![]() 11/23/10 - looking back towards the shopping mall |
![]() 11/23/10 - view of new club construction from officers club |
![]() 11/23/10 - here's an update view with more of the forms removed to expose the bare concrete, and the girders at the top remain about the same as the previous view |
|||
![]() 11/16/10 - this is the sign at the 4-way stop near teen center |
![]() 11/16/10 - overview of construction location |
![]() 11/16/10 - high-capacity sewer pipe sections at left |
![]() 11/16/10 - old corrugated pipe sections at right |
![]() 11/16/10 - working in front of Community Center |
![]() 11/16/10 - Songtan Blvd closed down to intersection |
![]() 11/16/10 - some work has to be done by hand |
![]() 11/16/10 - shopping mall at left, theater at center-right |
![]() 11/16/10 - there has been little to see of the building construction because the form have been blocking the view, but now you can see the forms are being removed starting at the left |
|||
![]() 11/16/10 - passing the construction vehicle entrance |
![]() 11/16/10 - exposed concrete and removing excess dirt |
![]() 11/16/10 - this will be one of the back doors of the club |
![]() 11/16/10 - another future back door at the left |
![]() 11/16/10 - construction materials stored in the building |
![]() 11/16/10 - view through temporary opening for machine |
![]() 11/16/10 - another view of materials stored inside |
![]() 11/16/10 - forms on ground indicate more concrete work |
![]() 10/26/10 - less than a week has passed since the last update and major vertical work is now seen. The Turumi Lodge is almost completely blocked from view and concrete pour should start soon. |
|||
![]() 10/21/10 - a week later and the final layer of concrete now fully encases the horizontal rebar. Rebar and vertical forms have been emplaced starting at the left to hold the concrete for the start of wall construction. |
|||
![]() 10/14/10 - rebar has been installed throughout the new club foundation and concrete laid over the dirt as the progress continues to finish the foundation and start the vertical work. |
|||
![]() 10/05/10 - just five days later and after weekend rain, progress continues with fill to go over the dirt and under the concrete. The area just to the right of center looks interesting. It has a non-standard shape, like an entertainment area. |
|||
![]() 9/30/10 - with dirt fill added, reinforcing bar now outlines the layout of the club's floor plan, room by room and it looks like concrete is being laid starting at the left side, maybe covered in plastic to let it cure slowly. |
|||
![]() 9/14/10 - the man in the blue shirt with the orange hose looks like he's involved in draining the accumulated rainwater, while the man to the right sitting on the concrete foundation wall looks like he's taking a break from working on the same task. |
|||
![]() 9/05/10 - the construction crew is back to work trying to pack in as much backfill as they can before the next typhoon hits Osan, with the clouds starting to darken as I write this caption. |
|||
![]() 8/31/10 - there's been a significant amount of rain in this post-monsoon period, but that doesn't seem to have slowed construction. I wanted to get this update before the next typhoon comes through this area, and it's scheduled to hit us two days from now. |
|||
![]() 8/19/10 - a lot of vertical progress with concrete is visible since the last look two weeks ago. The progress continues despite high humidity and high temperatures. |
|||
![]() 8/19/10 - here's a ground-level view of the site to give you a different perspective. Notice across the lot is that they've started stacking the construction 'office' boxes. |
![]() 8/19/10 - from the leftmost corner of the photo at left. |
||
![]() 8/03/10 - a new view shows the rebar in the previous photo has now been encased in concrete and more forms and rebar continue the march to the right as the club footing starts to take shape. |
|||
![]() 7/27/10 - here's an update showing more reinforcing bar being installed at the left and general progress elsewhere. The haze at the left side of the image is caused by water vapor blowing up from the air conditioning units. |
|||
![]() 7/15/10 - so much for predictions of monsoon rains delaying the construction as the monsoon front has hung around mostly off the southern coast leaving dry ground and generally clear skies in the Osan AB area. |
|||
![]() 7/03/10 - well, as predicted, the monsoon rains have started as shown here and progress will be slow until the rains stop and the ground dries a bit. |
|||
![]() 7/01/10 - considerable progress has been made in the month since the last photo as work progresses over the entire site. However, monsoon starts this weekend. |
|||
![]() 5/30/10 - if you compare this photo, taken two months after the previous one below, it's clear that the spring rains are slowing down the construction. |
|||
![]() 3/28/10 - and the rain continues to stymie any chance to pour concrete so the focus of work continues at the left side, but without concrete. |
|||
![]() 3/18/10 - more rain slowed construction again as seen in the water-filled holes that are supposed to contain the concrete main supports. Some work is being done at the left. |
|||
![]() 3/04/10 - the recent rains stopped construction for awhile and resulted in each of the main support holes filled with water and looking like mini swimming pools. |
|||
![]() 2/02/10 - considerable progress has been made with more precipitation-free days, and the weather, though still wintry, has been amenable with fewer work interruptions. |
|||
![]() 1/12/10 - the falling temperatures have brought construction to a halt. With morning temperature about -16°C (around 3°F), and with snow on the ground, work has stopped for the safety of the workers. |
|||
![]() 12/28/09 - the cold weather doesn't seem to have slowed workers in front of conex to the right of the dirt pile. When they started work this morning, the temperature was about -11°C (around 12°F) but they press on. |
|||
![]() 12/16/09 - holes have been dug and forms put in for the footings that will be poured. The moutain of dirt covered by netting is best viewed at ground level. |
|||
![]() 12/16/09 - this is a view from the Community Center side |
![]() 12/16/09 - another view from the Community Center side |
![]() 12/16/09 - artist's concept drawing of the finished club |
![]() 12/16/09 - construction details and planned completion date |
![]() 12/05/09 - some work is being done on Officers Club side |
![]() 12/05/09 - wind-driven snow does not stop the work |
![]() 12/05/09 - cloths on mud reduce tracking mud out of site just a bit |
![]() 12/05/09 - these machines await their new tasking |
![]() 11/30/09 - contruction has begun in earnest as can be seen here with the pilings going in to establish a solid foundation. This overview lets you see the eventual size of the building as seen by placement of pilings. |
|||
![]() 11/30/09 - large machine to drill holes for the pilings |
![]() 11/30/09- recent rain results in drill bit covered in mud |
![]() 11/30/09 - the area where the back of the new club will be |
![]() 11/30/09 - another view of the drilling machine |
![]() 10/29/09 - the new Challenger Enlisted Club construction has finally begun with a fence around the site. Expect good coverage as this is right next to Bldg 936 where the Retiree Activities Office is located. |
|||
![]() 9/07/08 - the new Challenger Club is still dormant, although some site preparation is going on at the left where utilities connections are being made |
|||
![]() 7/13/08 - the new Challenger Club will be built on this site next to the new Community Center; and the bare soil probably caused part of the drainage problem shown below |
|||
| New Challenger Enlisted Club | McPherson Community Center | ||
McPherson Community Center |
|||
![]() 7/13/08 - the new McPherson Community Center opened last week celebrating the event with a ribbon-cutting ceremony |
![]() 7/13/08 - a view of the front entrance to the new center |
||
![]() 7/13/08 - heavy rain overnight clogged this new drain |
![]() 7/13/08 - clogged drain caused the water to overflow |
![]() 7/13/08 - the overflow washed away newly-installed sod |
![]() 7/13/08 - and mud washed all the way down to Broadway |
![]() 5/25/08 - view of ongoing construction from chapel area |
![]() 5/25/08 - the Community Center has been exposed |
![]() 5/25/08 - landscaping and finishing work needed in front |
|
![]() 5/25/08 - the construction fence has been removed in front of the Community Center offering a good view of the facility and its environs |
|||
![]() 4/29/08 - a view of the Community Center and the now-cleared open area making my previous W-A-G about future use on Challenger Club construction way wrong. It was probably just convenient temporary storage |
|||
![]() 4/29/08 - structure for either trash receptacle or fuel tank |
![]() 4/29/08 - the power source for the facility |
![]() 4/29/08 - ground level view of the Community Center |
|
![]() 4/19/08 - here's the latest visual progress report on the construction of the new Community Center and the construction materials that will eventually be used for the new Challenger Club |
|||
![]() 3/30/08 - the Community Center construction progress and finishing work inside and out continues; and the construction materials continue to pile up for the next project here |
|||
![]() 3/09/08 - much of the current work on the Community Center is going on inside, although the front (not visible from here) is looking nearly complete. Challenger Club will be next in open area, and the likely site for a new parking garage is here |
|||
![]() 2/01/08 - a lot of progress has been made and the building looks closer to final finish and even more of the construction materials remain stored at the site |
|||
![]() 12/12/07 - the inside layer of the roof has been completed, providing weather protection for work inside. Roofing has been added atop the six concrete posts. |
|||
![]() 11/17/07 - the building continues to show good progress, with work started on the roof-supporting girders. Six concrete posts have been erected at the left side. |
|||
![]() 11/17/07 - a closer look at the building itself |
![]() 11/17/07 - roof construction as viewed from Hill 180 |
||
![]() 10/27/07 - two weeks later and the building continues its upward progress. I can't help but wonder about the large open area to the right. Looks large enough for a parking garage. |
|||
![]() 10/14/07 - construction progress continues to benefit from the good weather. |
|||
![]() 10/07/07 - good weather shows the increased pace of construction reflected in the changes since the last update. |
|||
![]() 9/16/07 - a week later and the rains had continued to keep the construction side inundated. Coming week will probably be no better with typhoon rains and wind predicted. |
|||
![]() 9/08/07 - this view shows muddy working conditions |
![]() 9/08/07 - vehicle tracks show parking lot was covered |
![]() 9/08/07 - wall removed to accommodate the mud flow |
![]() 9/08/07 - despite rains, foundation work continues |
![]() 9/08/07 - unseasonal rains (post-monsoon) have slowed but not stopped the construction. A tent has been added at the right to allow workmen to continue some work despite the weather. |
|||
![]() 8/18/07 - the forms for the foundation of the community center building are clearly visible at the left side. Wonder what will be occupying the large area at the right. A ski jump? |
|||
![]() 7/31/07 - another two weeks since the last photo and more significant progress is seen at the left side where forms are in place indicating the that construction should be starting soon |
|||
![]() 7/15/07 - this is an early morning photo taken before the construction personnel have arrived and it provides the opportunity to see the progress over the two weeks since the photo below |
|||
![]() 6/30/07 - lot of change has occurred in the site preparation for the Community Activities Center. Looks like they're trying to build a mountain in the middle, but it's probably just overcoming drainage problems. |
|||
![]() 6/23/07 - at the left, some of the piers that were inserted have been cut down and stack of "tops" can be seen. Drainage is a problem and pump is visible at the bottom center of the scene. A high-detail image (1.3 MB) can be viewed here. |
|||
![]() 6/15/07 - an updated look from the Officers Club parking lot at the progress of site preparation for Osan's new 6/15/07 - Community Activities Center (CAC) (compare pilings at left with image of 6/10/07) |
|||
![]() 6/15/07 - a different perspective on the CAC site preparation looking from the second floor side entrance to Building 936, the Personnel building |
|||
![]() 6/15/07 - the parking area at the rear of the CAC site has been striped and the bumper block have been installed, so everything's back to normal (sort of) |
|||
![]() 6/15/07 - a view of the cleared site from the Library side |
![]() 6/10/07 - the pile driver has been emplacing concrete poles for a stable foundation upon which to build. |
||
![]() 5/26/07 - The site is clean and ready for the site preparation work of bringing in the utilities to match the new building's needs. |
![]() 5/26/07 - a look at the cleared site; library is at the rear |
||
![]() 5/26/07 - parking area paving has been completed behind the Community Activities Center site. The finishing work of installing the concrete stop blocks and painting lines can now proceed. |
|||
![]() 5/19/07 - parking area behind CAC construction is repaved |
![]() 5/19/07 - parking will serve the CAC and surrounding buildings |
![]() 5/19/07 - concrete stop blocks for the parking spaces |
![]() 5/19/07 - forms used to make the concrete stop blocks |
![]() 4/28/07 - construction fence has gone up around old BX |
![]() 4/28/07 - the port-a-potty is in place for workers |
![]() 4/28/07 - the old building soon to be removed |
![]() 4/28/07 - digging already started at library end |
![]() Drawing of the Community Activities Center when finished |
![]() The contract information with completion date Jun 2008 |
![]() 4/28/07 - workmen excavating a part of the parking area |
![]() 4/28/07 - curved designs being dug into the excavated area |