| Middle and High Schools | Commissary and School Parking Garage | ||
Middle and High Schools |
|||
|---|---|---|---|
![]() 10/17/09 - the renovation of the high school sports field has been completed and the result is really beautiful. The field is covered with artificial turf to avoid previous problems caused by monsoon rains and poor drainage. |
|||
![]() 8/15/09 - in preparation for the coming school season (and beyond), the sport field behind the high school and new middle school is being renovated by a Korean contractor. The scheduled closure is described in this sign. |
|||
![]() 6/19/09 - middle school complete, starting at the back |
![]() 6/19/09 - construction at the back was mostly invisible |
![]() 6/19/09 - now we know that it's a combination facility |
![]() 6/19/09 - concrete pad turns out to be bicycle parking |
![]() 6/19/09 - looking across front of multipurpose facility |
![]() 6/19/09 - what was fenced off area is now nicely landscaped |
![]() 6/19/09 - looking across back of multipurpose facility |
![]() 6/19/09 - behind multipurpose facility is basketball/tennis court |
![]() 6/19/09 - here is the entire front view of the middle school to complete this construction photo series |
|||
![]() 6/19/09 - here's a first look at music school added behind HS |
![]() 6/19/09 - a look inside shows a lot of finishing work remains |
![]() 6/19/09 - a panoramic view of the middle and high schools to complete the DoDDS school construction series |
|
![]() 5/17/09 - here's an updated look at the middle school |
![]() 5/17/09 - a view of the school from top of parking garage |
![]() 5/17/09 - closer look at front construction area |
![]() 5/17/09 - concrete pad with stand for something (fuel tank?) |
![]() 5/17/09 - part of the back of the middle school to show the progess of the construction |
![]() 5/17/09 - another concrete pad with stand for something |
||
![]() 5/17/09 - an updated look at the gym addition at the back of the middle school |
![]() 5/17/09 - a side look at the gym addition showing depth |
||
![]() 2/20/09 - much of the construction fence is removed to allow a better view of the back of the middle school |
![]() 2/20/09 - view of front of school from parking garage |
||
![]() 2/01/09 - a panoramic view of the back of the middle school and landscaping work is progressing |
![]() 2/01/09 - here's a view of the front of the school |
![]() 2/01/09 - after snow melted, workers contended with mud |
|
![]() 1/02/09 - an update view of the back of the school |
![]() 1/02/09 - worker trying to decipher the plan |
![]() 1/02/09 - front of the school looking better |
|
![]() 12/14/08 - a view of the middle school seen from the top of the parking garage |
![]() 12/14/08 - updated view showing roof nearly complete |
||
![]() 11/30/08 - this is an updated view of the roof seen from Hill 170 |
![]() 11/30/08 - the side of the school is showing great progess |
![]() 11/30/08 - circle on front will not be a "Hope" symbol |
|
![]() 11/11/08 - girders now being installed over roof supports |
![]() 11/11/08 - a view of the side facing Mustang Valley Village |
||
![]() 11/09/08 - Hill 170 view of middle school construction |
![]() 11/09/08 - a closer look at the work on top shows roof supports in place with a dividing structure separating a smaller area at the right |
||
![]() 11/02/08 - a view of the school from across street |
![]() 11/02/08 - view of middle school construction from Songtan Blvd |
![]() 11/02/08 - a more vertical look at the back of school construction site |
|
![]() 11/02/08 - the insulation work in progress on side |
![]() 11/02/08 - small part insulation stacked and ready |
||
![]() 10/25/08 - a view of the school from parking garage |
![]() 10/25/08 - view of middle school construction from Songtan Blvd |
![]() 10/25/08 - looking at the back of school construction site |
![]() 10/25/08 - another view of the back of the school construction |
![]() 9/14/08 - school construction seen from Hill 170 |
![]() 9/13/08 - view of middle school construction |
![]() 9/13/08 - closer look at construction at rear |
![]() 9/07/08 - side of middle school facing high school |
![]() 9/07/08 - a sweeping side view of the high school expansion, related bus parking, middle school construction in the background and the sports field |
|||
![]() 8/24/08 - a long view of the school and parking garage |
![]() 8/24/08 - cramped space and increasing building height led me to try this vertical pan view (hi-rez image) |
||
![]() 8/24/08 - side view of the front of the building |
|||
![]() 8/24/08 - one of the infrequent views of the middle school side nearest the officers dorm Bldg 736 |
|||
![]() 8/24/08 - a view of the middle school side facing the high school |
![]() 8/16/08 - walkway is covered as finish work proceeds |
![]() 8/16/08 - front lawn is almost back to normal |
|
![]() 8/16/08 - a wider look at the high school addition and the other construction going on at the rear of the school |
|||
![]() 8/03/08 - another rare look at the high school expansion that looks like it's nearly completed |
![]() 8/03/08 - completing bus loading area next to school |
||
![]() 8/03/08 - an update view of the construction site from the sidewalk near the officers dorm |
![]() 8/03/08 - and a different view from the site entrance adjacent to the high school |
||
![]() 8/03/08 - another rare look at the high school expansion that looks like it's nearly completed |
![]() 8/03/08 - completing bus loading area next to school |
||
![]() 8/03/08 - start on walkway between parking and school |
![]() 8/03/08 - opposite view of walkway on school side |
![]() 8/03/08 - opening on parking garage to connect to walkway |
|
![]() 6/08/08 - overlooking front construction site from the sidewalk near the officers dorm |
![]() 6/08/08 - a look back towards rear of the site |
||
![]() 6/08/08 - the foundation is laid for construction at front of the middle school construction site |
![]() 6/08/08 - a look a construction at the rear of the site |
||
![]() 6/08/08 - a view from above at the construction shown in the above photo |
![]() 6/08/08 - a rare look at the high school expansion work |
||
![]() 5/10/08 - a new look at the progress of construction of the middle school as the vertical construction and expanded foundation work continue |
|||
![]() 5/10/08 - overview of middle school construction site |
![]() 5/10/08 - a look from ground level at the construction area near the front of the site that now gets more attention as the foundation is laid |
||
![]() 5/04/08 - ground-level view of the middle school construction site taken from the Songtan Blvd. Equipment at left is seen in first photo below taken in opposite side view from officers dorm |
![]() 5/04/08 - construction equipment busily working |
||
![]() 5/04/08 - construction equipment busily working |
![]() 5/04/08 - another view looking at the larger area |
![]() 5/04/08 - the area behind and to the left |
|
![]() 3/30/08 - this is a ground-level view of the middle school construction site taken from the Songtan Blvd. It looks a lot more crowded than view below. |
|||
![]() 3/09/08 - this is a ground-level view of the middle school construction site taken from the Building 736 BOQ side. The high school is in the background. |
|||
![]() 3/09/08 - overview of middle school site from Songtan Blvd |
![]() 3/09/08 - the footings for the school building (from Bldg 736) |
![]() 3/09/08 - front of site with parking garage site behind it |
|
![]() 3/09/08 - more construction going on behind school site |
![]() 3/09/08 - this is going on very close to the enlisted dorms |
![]() 3/09/08 - interesting sign for a sidewalk that's going nowhere |
|
![]() 2/02/08 - installation of the concrete pillars continues at the middle school site and I'm sure residents of adjacent Bldg 736 BOQ will be happy when it's done |
|||
![]() 2/02/08 - looking down on the construction site from Hill 170 |
![]() 2/02/08 - view of site from hole in fence next to Bldg 736 |
![]() 2/02/08 - looking down on pillar pounding area from Bldg 736 |
![]() 2/02/08 - construction viewed from Bdlg 736 |
![]() 12/23/07 - construction at the front of the high school as the surrounding construction expands |
|||
![]() 12/23/07 - construction at the front of the high school as the surrounding construction expands |
|||
![]() 12/23/07 - new construction continues at the rear of the high school and note the bare surface of the sport field at the right rear |
|||
![]() 12/13/07 - front of high school disrupted by construction |
![]() 11/17/07 - site preparation for construction of the middle school continues adjacent to the high school |
||
![]() 11/17/07 - from Songtan Blvd to Elementary School |
![]() 11/17/07 - continue straight to school, or right to Commissary |
![]() 11/17/07 - Commissary parking is affected by the construction |
![]() 11/17/07 - Commissary traffic flow is temporarily affected |
![]() 10/27/07 - middle school construction continues as shown here. Notice the car at the left — check out this blowup to see who's not carrying his share of the workload. |
|||
![]() 10/27/07 - construction impedes smooth traffic flow |
![]() 10/27/07 - digging is related to middle school construction |
![]() 10/27/07 - elementary school road construction overview |
|
![]() 10/27/07 - here's a closer look at the road construction and shows that the Elementary School info sign has been relocated |
![]() 10/27/07 - will this event disrupt construction, or vice versa |
||
![]() 9/16/07 - columns for the middle school are rising at the rear as the expansion of Osan DoDDS continues |
|||
![]() 8/18/07 - construction overview coming from gate |
![]() 8/18/07 - to the right, there is extensive construction activity near the sports field as the high school expansion proceeds |
||
![]() 8/18/07 - rearranging the sidewalk is part of the work |
![]() 8/18/07 - project manager uses portable buildings |
![]() 8/18/07 - temporary buildings such as this being replaced |
![]() 8/18/07 - construction area next to officers' dorm |
![]() 8/19/07 - construction progesses where the middle school will go to the right and the music facility will go into the area straight back |
|||
![]() 7/31/07 - construction started next to Osan High School |
![]() 7/31/07 - construction will comprise three new structures |
![]() 7/31/07 - an extension will be added to the high school |
![]() 7/31/07 - a middle school and music facility will go here |
| Middle and High Schools | Commissary and School Parking Garage | ||
Parking Garage |
|||
![]() 12/14/09 - the next day and a different view of the area |
![]() 12/14/09 - more workers were visible on this Monday |
![]() 12/14/09 - the man on the platform is welding a support |
![]() 12/14/09 - and drainage pipes are being added as seen here |
![]() 12/13/09 - updating the progress on lower half of third story |
![]() 12/13/09 - worker appears to be inspecting work done |
![]() 12/13/09 - a look down the entire length of the area |
![]() 12/13/09 - plates to be attached rest against pillars |
![]() 12/06/09 - it looks like additional reinforcing is being added |
![]() 12/06/09 - steel plates are added to ceiling for attachment |
![]() 12/06/09 - then reinforcement is attached to ceiling and post |
![]() 12/06/09 - upper half of third story is nearly completed |
![]() 12/14/08 - the running track and basketball court seen from a different angle now that it's open and available for use |
![]() 12/14/08 - here's the track distance information |
||
![]() 10/25/08 - the icing on the cake, so to speak, here is the top of the parking garage consisting of four tennis courts, a basketball court and a track |
|||
![]() 10/15/08 - two outside and one inside stairway (shown here) |
![]() 10/15/08 - this is the skybridge and stairway to the school |
![]() 10/15/08 - looking through the skybridge towards the school |
![]() 10/25/08 - some shoppers have started parking inside |
![]() 10/16/08 - ramp to parking at front (see at right) |
![]() 10/16/08 - extensive sprinkler system througout facility |
![]() 10/15/08 - a unisex toilet is available for emergencies |
![]() 10/15/08 - an elevator is provided for the handicapped |
![]() 10/15/08 - only the ground floor is open, others still closed off |
![]() 10/15/08 - this is a big relief for Commissary shoppers |
![]() 10/15/08 - the sign gives information on the facility |
![]() 10/15/08 - still-closed ramp to upper floor parking areas |
![]() 10/15/08 - there's this sign in front of parking garage |
![]() 10/15/08 - the railing is completed and painted |
![]() 10/15/08 - approaching the parking garage entrance |
![]() 10/15/08 - the garage is open to Commissary parking |
![]() 10/15/08 - approaching the parking garage entrance |
![]() 10/15/08 - the garage is open to Commissary parking |
![]() 10/15/08 - only the ground floor is open, others still closed off |
![]() 10/15/08 - this is a big relief for Commissary shoppers |
![]() 10/12/08 - the sidewalk around the parking garage is nearly complete and a railing along front sidewalk has been started |
![]() 10/12/08 - sidewalk railing on school side is complete |
||
![]() 10/11/08 - view of school construction seen from Hill 170 |
![]() 10/05/08 - sidewalk on Mustang Village side is done |
![]() 10/05/08 - sidewalk on Commissary side is done |
![]() 10/05/08 - sidewalk near elem school entrance still in work |
![]() 9/14/08 - top of parking garage viewed from Hill 170 |
![]() 9/13/08 - back of parking garage facing Commissary |
![]() 9/13/08 - stairway leading to upper floors |
![]() 9/13/08 - information sign inside the stairway |
![]() 9/13/08 - sidewalk is starting the take shape |
![]() 9/07/08 - pedestrian overpass as seen heading to main gate |
![]() 9/07/08 - walkway as seen returning from main gate |
![]() 9/07/08 - scaffolding at side, ready for pickup |
![]() 9/07/08 - a look at the current state of construction of the parking garage to serve the Commissary and the schools. Unevenness of lines is due to photo stitching, not poor construction. |
|||
![]() 8/24/08 - the finishing work continues on the outside as the construction work continues on the other side and top |
![]() 8/16/08 - bolted-on stanchions that will support top cover |
||
![]() 8/16/08 - a look at the current state of construction of the parking garage to serve the Commissary and the schools |
![]() 8/16/08 - light at the end of the tunnel is the opposite entrance |
||
![]() 8/03/08 - a look at the current state of construction of the parking garage to serve the Commissary and the schools |
![]() 8/03/08 - construction company sign ( whatever it means) |
||
![]() 6/28/08 - third floor construction is shown at MVV end of bldg |
![]() 6/28/08 - third floor construction proceeds across garage |
![]() 6/28/08 - from the opposite side, preparation for third floor construction has begun |
|
![]() 5/08/08 - the parking garage construction progresses from left to right as seen in the second floor construction at the left |
![]() 6/08/08 - a long view of construction from ground level |
||
![]() 6/08/08 - once again, a different view of the parking garage construction from road to the ROKAF area. Two workers ...oops ... supervisors take a break at the near end while a crews works away in the distance. |
|||
![]() 5/25/08 - workers get early start with cool morning weather |
![]() 5/25/08 - MVV residents not enjoying early morning noise |
![]() 5/25/08 - the second floor construction is progressing |
![]() 5/25/08 - but not for the entire length of the bldg |
![]() 5/25/08 - sneaking a peek at the far end through fence |
![]() 5/25/08 - a different view of the parking garage construction from road to the ROKAF area. Three family housing areas and Sr NCO dorm are visible in background |
||
![]() 5/10/08 - a closer look at the parking garage construction with the extensive bracing to support drying floor above. The wood that was seen being delivered last week has been put to good use |
![]() 5/10/08 - this machine was rescuing a stuck forklift |
||
![]() 5/04/08 - materials unloaded, stacked for easy access to site |
![]() 5/04/08 - from the opposite side, a wider view of the construction site |
||
![]() 5/04/08 - a wider view of the construction looking down from the ROKAF side |
|||
![]() 4/19/08 - a ground-level view of the parking garage site, showing the development of the ground level parking. |
|||
![]() 4/13/08 - here's a different perspective of the parking garage construction from the ROKAF access road side. |
|||
![]() 3/30/08 - perspective view of the parking garage site |
![]() 3/30/08 - from the opposite side, a wider view of the construction site |
||
![]() 3/30/08 - a ground-level view of the parking garage site, with limited view because of stacked materials. |
|||
![]() 3/09/08 - site stabilization is complete and the footings for the parking garage are being installed. |
|||
![]() 1/05/08 - a nice overview of the parking garage site |
![]() 1/05/08 - the parking garage construction site as seen from ground level with high school in the background |
||
![]() 12/23/07 - the site preparation continues for the three-story parking garage with pile drivers emplacing the concrete posts for a stable foundation |
|||
![]() 11/24/07 - traffic is temporarily detoured for unimpeded work |
![]() 11/24/07 - the front fence has been temporarily removed to facilitate work allowing for this look across the entire work site |
||
![]() 7/31/07 - construction has started next to the Osan HS |
![]() 7/31/07 - construction will comprise three new structures |
![]() 7/31/07 - an extension will be added to the high school |
![]() 7/31/07 - a middle school and music facility will go here |
![]() 9/16/07 - rain delayed the road reopening more than two weeks |
![]() 9/16/07 - Burger King at this location is history as the preparation for the new three-story parking garage here continues |
||
![]() 9/08/07 - Popeye's is history, only a slab is left |
![]() 9/08/07 - Popeye's site now stores construction materials |
![]() 9/08/07 - with Popeye's gone, can Burger King be far behind |
![]() 9/08/07 - now we have to go where you went |
![]() 8/18/07 - lots of work involved in putting in new road |
![]() 8/18/07 - looking from the back the site is really busy |
![]() 7/31/07 - Popeyes will not be replaced, say "bye-bye, Popeyes" — WRONG! |
A mobile Burger King trailer is currently parked at the Shopping Mall. It will be used until the new Burger King dual-food facility is built across from the MiG Alleys Bowling Center Correction to caption at left: Popeye's will reappear when the new facility is completed. |
![]() 7/15/07 - this parking area next to Burger King will go away |
![]() 7/31/07 - to make room for the construction of a new access road to the elementary school, and the road is being moved to make room for a parking garage |
||